Items where Author is "Health and Executive Safety, "
Up a level |
appendix 4 the health and safety file
This Appendix gives guidance on the preparation, provision and retention of a health and safety file and the actions on each dutyholder.
Appendix 5 shows how the health and safety file relates to and influences other types of information during a construction project involving more than one contractor.
The health and safety file is defined as a file appropriate to the characteristics of
the project, containing relevant health and safety information to be taken into
account during any subsequent project. The file is only required for projects
involving more than one contractor.
as constructed information
The file must contain information about the current project likely to be needed to ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion:
(b) any hazards that have not been eliminated through the design and construction processes, and how they have been addressed (eg surveys or other information concerning asbestos or contaminated land);
as-built drawing
The file must contain information about the current project likely to be needed to ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion:
(a) a brief description of the work carried out;
(b) any hazards that have not been eliminated through the design and construction processes, and how they have been addressed (eg surveys or other information concerning asbestos or contaminated land);
(c) key structural principles (eg bracing, sources of substantial stored energy – including pre- or post-tensioned members) and safe working loads for floors and roofs;
(d) hazardous materials used (eg lead paints and special coatings);
(e) information regarding the removal or dismantling of installed plant and equipment (eg any special arrangements for lifting such equipment);
(f) health and safety information about equipment provided for cleaning or
maintaining the structure;
(g) the nature, location and markings of significant services, including underground cables; gas supply equipment; fire-fighting services etc;
(h) information and as-built drawings of the building, its plant and equipment (eg the means of safe access to and from service voids and fire doors).
The file must contain information about the current project likely to be needed to ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion:
(h) information and as-built drawings of the building, its plant and equipment (eg the means of safe access to and from service voids and fire doors).
asbestos survey
The file must contain information about the current project likely to be needed to ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion:
(a) a brief description of the work carried out;
(b) any hazards that have not been eliminated through the design and construction processes, and how they have been addressed (eg surveys or other information concerning asbestos or contaminated land);
(c) key structural principles (eg bracing, sources of substantial stored energy – including pre- or post-tensioned members) and safe working loads for floors and roofs;
(d) hazardous materials used (eg lead paints and special coatings);
(e) information regarding the removal or dismantling of installed plant and equipment (eg any special arrangements for lifting such equipment);
(f) health and safety information about equipment provided for cleaning or
maintaining the structure;
(g) the nature, location and markings of significant services, including underground cables; gas supply equipment; fire-fighting services etc;
(h) information and as-built drawings of the building, its plant and equipment (eg the means of safe access to and from service voids and fire doors).
The file must contain information about the current project likely to be needed to ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion:
(b) any hazards that have not been eliminated through the design and construction processes, and how they have been addressed (eg surveys or other information concerning asbestos or contaminated land);
audit documentation
The principal designer, in cooperation with other members of the project team,
must also ensure that the file is appropriately updated, reviewed and revised to
ensure it takes account of any changes that occur as the project progresses.
availability
The client must then retain the file and ensure it is available to anyone who may
need it for as long as it is relevant – normally the lifetime of the building – to enable
them to comply with health and safety requirements during any subsequent project.
It can be kept electronically, on paper, on film, or any other durable form.
If a client disposes of their interest in the building, they must give the file to the
individual or organisation who takes on the client duties and ensure that the new
client is aware of the nature and purpose of the file. If they sell part of a building,
any relevant information in the file must be passed or copied to the new owner. If
the client leases out all or part of the building, arrangements should be made for
the file to be made available to leaseholders. If the leaseholder acts as a client for a
future construction project, the leaseholder and the original client must arrange for
the file to be made available to the new principal designer.
brief
The file must contain information about the current project likely to be needed to ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion:
(a) a brief description of the work carried out;
building
If a client disposes of their interest in the building, they must give the file to the
individual or organisation who takes on the client duties and ensure that the new
client is aware of the nature and purpose of the file. If they sell part of a building,
any relevant information in the file must be passed or copied to the new owner. If
the client leases out all or part of the building, arrangements should be made for
the file to be made available to leaseholders. If the leaseholder acts as a client for a
future construction project, the leaseholder and the original client must arrange for
the file to be made available to the new principal designer.
building survey
The file must contain information about the current project likely to be needed to ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion:
(a) a brief description of the work carried out;
(b) any hazards that have not been eliminated through the design and construction processes, and how they have been addressed (eg surveys or other information concerning asbestos or contaminated land);
(c) key structural principles (eg bracing, sources of substantial stored energy – including pre- or post-tensioned members) and safe working loads for floors and roofs;
(d) hazardous materials used (eg lead paints and special coatings);
(e) information regarding the removal or dismantling of installed plant and equipment (eg any special arrangements for lifting such equipment);
(f) health and safety information about equipment provided for cleaning or
maintaining the structure;
(g) the nature, location and markings of significant services, including underground cables; gas supply equipment; fire-fighting services etc;
(h) information and as-built drawings of the building, its plant and equipment (eg the means of safe access to and from service voids and fire doors).
ce marking
The file must contain information about the current project likely to be needed to ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion:
(a) a brief description of the work carried out;
(b) any hazards that have not been eliminated through the design and construction processes, and how they have been addressed (eg surveys or other information concerning asbestos or contaminated land);
(c) key structural principles (eg bracing, sources of substantial stored energy – including pre- or post-tensioned members) and safe working loads for floors and roofs;
(d) hazardous materials used (eg lead paints and special coatings);
(e) information regarding the removal or dismantling of installed plant and equipment (eg any special arrangements for lifting such equipment);
(f) health and safety information about equipment provided for cleaning or
maintaining the structure;
(g) the nature, location and markings of significant services, including underground cables; gas supply equipment; fire-fighting services etc;
(h) information and as-built drawings of the building, its plant and equipment (eg the means of safe access to and from service voids and fire doors).
The file must contain information about the current project likely to be needed to ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion:
(g) the nature, location and markings of significant services, including underground cables; gas supply equipment; fire-fighting services etc;
client
The principal designer must prepare the health and safety file. They are
accountable to the client and should liaise closely to agree the structure and
content of the file as soon as practicable after appointment. In preparing the file,
the principal designer should expect the client to provide any health and safety file
that may exist from an earlier project.
The principal designer must prepare the health and safety file. They are
accountable to the client and should liaise closely to agree the structure and
content of the file as soon as practicable after appointment. In preparing the file,
the principal designer should expect the client to provide any health and safety file
that may exist from an earlier project.
The principal designer must pass the updated file to the client at the end of the
project. In doing this, they should ensure the client understands the structure and
content of the file and its significance for any subsequent project. If the principal
designer’s appointment finishes before the end of the project, they must pass the
file to the principal contractor who must then take on responsibility for it. In doing
this, the principal designer should ensure the principal contractor is aware of any
outstanding issues that may need to be taken into account when reviewing,
updating and revising the file.
The principal designer must pass the updated file to the client at the end of the
project. In doing this, they should ensure the client understands the structure and
content of the file and its significance for any subsequent project. If the principal
designer’s appointment finishes before the end of the project, they must pass the
file to the principal contractor who must then take on responsibility for it. In doing
this, the principal designer should ensure the principal contractor is aware of any
outstanding issues that may need to be taken into account when reviewing,
updating and revising the file.
Where the principal designer’s appointment finishes before the end of the
project, the principal contractor must take on responsibility for ensuring that the file
is reviewed, updated and revised for the remainder of the project. At the end of the
project the principal contractor must pass the file to the client. In doing this, they
should ensure the client understands the structure and content of the file and its
significance for any subsequent project.
Where the principal designer’s appointment finishes before the end of the
project, the principal contractor must take on responsibility for ensuring that the file
is reviewed, updated and revised for the remainder of the project. At the end of the
project the principal contractor must pass the file to the client. In doing this, they
should ensure the client understands the structure and content of the file and its
significance for any subsequent project.
The client must ensure that the principal designer prepares the health and safety
file for a project. As the project progresses, the client must ensure that the principal
designer regularly updates, reviews and revises the health and safety file to take
account of the work and any changes that have occurred. The client should be
aware that if the principal designer’s appointment finishes before the end of the
project, the principal designer must pass the health and safety file to the principal
contractor, who then must take on the responsibility for the file.
Information must be in a convenient form, clear, concise and easily understandable.
The client must ensure that the principal designer prepares the health and safety
file for a project. As the project progresses, the client must ensure that the principal
designer regularly updates, reviews and revises the health and safety file to take
account of the work and any changes that have occurred. The client should be
aware that if the principal designer’s appointment finishes before the end of the
project, the principal designer must pass the health and safety file to the principal
contractor, who then must take on the responsibility for the file.
Information must be in a convenient form, clear, concise and easily understandable.
Once the project is finished, the client should expect the principal designer to
pass them the health and safety file. In cases where the principal designer has left
the project before it finishes, it will be for the principal contractor to pass the file to
the client.
Once the project is finished, the client should expect the principal designer to
pass them the health and safety file. In cases where the principal designer has left
the project before it finishes, it will be for the principal contractor to pass the file to
the client.
The client must then retain the file and ensure it is available to anyone who may
need it for as long as it is relevant – normally the lifetime of the building – to enable
them to comply with health and safety requirements during any subsequent project.
It can be kept electronically, on paper, on film, or any other durable form.
The client must then retain the file and ensure it is available to anyone who may
need it for as long as it is relevant – normally the lifetime of the building – to enable
them to comply with health and safety requirements during any subsequent project.
It can be kept electronically, on paper, on film, or any other durable form.
If a client disposes of their interest in the building, they must give the file to the
individual or organisation who takes on the client duties and ensure that the new
client is aware of the nature and purpose of the file. If they sell part of a building,
any relevant information in the file must be passed or copied to the new owner. If
the client leases out all or part of the building, arrangements should be made for
the file to be made available to leaseholders. If the leaseholder acts as a client for a
future construction project, the leaseholder and the original client must arrange for
the file to be made available to the new principal designer.
If a client disposes of their interest in the building, they must give the file to the
individual or organisation who takes on the client duties and ensure that the new
client is aware of the nature and purpose of the file. If they sell part of a building,
any relevant information in the file must be passed or copied to the new owner. If
the client leases out all or part of the building, arrangements should be made for
the file to be made available to leaseholders. If the leaseholder acts as a client for a
future construction project, the leaseholder and the original client must arrange for
the file to be made available to the new principal designer.
construction lead
The file must contain information about the current project likely to be needed to ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion:
(a) a brief description of the work carried out;
(b) any hazards that have not been eliminated through the design and construction processes, and how they have been addressed (eg surveys or other information concerning asbestos or contaminated land);
(c) key structural principles (eg bracing, sources of substantial stored energy – including pre- or post-tensioned members) and safe working loads for floors and roofs;
(d) hazardous materials used (eg lead paints and special coatings);
(e) information regarding the removal or dismantling of installed plant and equipment (eg any special arrangements for lifting such equipment);
(f) health and safety information about equipment provided for cleaning or
maintaining the structure;
(g) the nature, location and markings of significant services, including underground cables; gas supply equipment; fire-fighting services etc;
(h) information and as-built drawings of the building, its plant and equipment (eg the means of safe access to and from service voids and fire doors).
construction phase
There should be enough detail to allow the likely risks to be identified and
addressed by those carrying out the work. However, the level of detail should be
proportionate to the risks. The file should not include things that will be of no help
when planning future construction work such as pre-construction information, the
construction phase plan, contractual documents, safety method statements etc.
Information must be in a convenient form, clear, concise and easily understandable.
contaminant
The file must contain information about the current project likely to be needed to ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion:
(b) any hazards that have not been eliminated through the design and construction processes, and how they have been addressed (eg surveys or other information concerning asbestos or contaminated land);
contractor
This Appendix gives guidance on the preparation, provision and retention of a health and safety file and the actions on each dutyholder.
Appendix 5 shows how the health and safety file relates to and influences other types of information during a construction project involving more than one contractor.
The principal designer must pass the updated file to the client at the end of the
project. In doing this, they should ensure the client understands the structure and
content of the file and its significance for any subsequent project. If the principal
designer’s appointment finishes before the end of the project, they must pass the
file to the principal contractor who must then take on responsibility for it. In doing
this, the principal designer should ensure the principal contractor is aware of any
outstanding issues that may need to be taken into account when reviewing,
updating and revising the file.
For the duration of the principal designer’s appointment, the principal
contractor plays a secondary role in ensuring the health and safety file is fit for
purpose. They must provide the principal designer with any relevant information that
needs to be included in the health and safety file.
Where the principal designer’s appointment finishes before the end of the
project, the principal contractor must take on responsibility for ensuring that the file
is reviewed, updated and revised for the remainder of the project. At the end of the
project the principal contractor must pass the file to the client. In doing this, they
should ensure the client understands the structure and content of the file and its
significance for any subsequent project.
Where the principal designer’s appointment finishes before the end of the
project, the principal contractor must take on responsibility for ensuring that the file
is reviewed, updated and revised for the remainder of the project. At the end of the
project the principal contractor must pass the file to the client. In doing this, they
should ensure the client understands the structure and content of the file and its
significance for any subsequent project.
The contractor has no specific duties placed on them in relation to the health
and safety file.
The health and safety file is defined as a file appropriate to the characteristics of
the project, containing relevant health and safety information to be taken into
account during any subsequent project. The file is only required for projects
involving more than one contractor.
The client must ensure that the principal designer prepares the health and safety
file for a project. As the project progresses, the client must ensure that the principal
designer regularly updates, reviews and revises the health and safety file to take
account of the work and any changes that have occurred. The client should be
aware that if the principal designer’s appointment finishes before the end of the
project, the principal designer must pass the health and safety file to the principal
contractor, who then must take on the responsibility for the file.
Information must be in a convenient form, clear, concise and easily understandable.
Once the project is finished, the client should expect the principal designer to
pass them the health and safety file. In cases where the principal designer has left
the project before it finishes, it will be for the principal contractor to pass the file to
the client.
Where it is not possible to eliminate health and safety risks when preparing or
modifying designs, designers must ensure appropriate information is included in the
health and safety file about the reasonably practicable steps they have taken to
reduce or control those risks. This will involve liaising with:
(a) the principal designer, in helping them carry out their duty to prepare, update,
review and revise the health and safety file. This should continue for as long as
the principal designer’s appointment on the project lasts; or
(b) the principal contractor, where design work is carried out after the principal
designer’s appointment has finished and where changes need to be made to
the health and safety file. In these circumstances, it will be the principal
contractor’s duty to make those changes, but the designer must ensure that
the principal contractor has the appropriate information to update the file.
This information should be provided to the principal designer and principal
contractor as early as possible before the designer’s work ends on the project.
design lead
The file must contain information about the current project likely to be needed to ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion:
(a) a brief description of the work carried out;
(b) any hazards that have not been eliminated through the design and construction processes, and how they have been addressed (eg surveys or other information concerning asbestos or contaminated land);
(c) key structural principles (eg bracing, sources of substantial stored energy – including pre- or post-tensioned members) and safe working loads for floors and roofs;
(d) hazardous materials used (eg lead paints and special coatings);
(e) information regarding the removal or dismantling of installed plant and equipment (eg any special arrangements for lifting such equipment);
(f) health and safety information about equipment provided for cleaning or
maintaining the structure;
(g) the nature, location and markings of significant services, including underground cables; gas supply equipment; fire-fighting services etc;
(h) information and as-built drawings of the building, its plant and equipment (eg the means of safe access to and from service voids and fire doors).
drawing building
The file must contain information about the current project likely to be needed to ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion:
(a) a brief description of the work carried out;
(b) any hazards that have not been eliminated through the design and construction processes, and how they have been addressed (eg surveys or other information concerning asbestos or contaminated land);
(c) key structural principles (eg bracing, sources of substantial stored energy – including pre- or post-tensioned members) and safe working loads for floors and roofs;
(d) hazardous materials used (eg lead paints and special coatings);
(e) information regarding the removal or dismantling of installed plant and equipment (eg any special arrangements for lifting such equipment);
(f) health and safety information about equipment provided for cleaning or
maintaining the structure;
(g) the nature, location and markings of significant services, including underground cables; gas supply equipment; fire-fighting services etc;
(h) information and as-built drawings of the building, its plant and equipment (eg the means of safe access to and from service voids and fire doors).
The file must contain information about the current project likely to be needed to ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion:
(h) information and as-built drawings of the building, its plant and equipment (eg the means of safe access to and from service voids and fire doors).
duties
The contractor has no specific duties placed on them in relation to the health
and safety file.
If a client disposes of their interest in the building, they must give the file to the
individual or organisation who takes on the client duties and ensure that the new
client is aware of the nature and purpose of the file. If they sell part of a building,
any relevant information in the file must be passed or copied to the new owner. If
the client leases out all or part of the building, arrangements should be made for
the file to be made available to leaseholders. If the leaseholder acts as a client for a
future construction project, the leaseholder and the original client must arrange for
the file to be made available to the new principal designer.
Where it is not possible to eliminate health and safety risks when preparing or
modifying designs, designers must ensure appropriate information is included in the
health and safety file about the reasonably practicable steps they have taken to
reduce or control those risks. This will involve liaising with:
(a) the principal designer, in helping them carry out their duty to prepare, update,
review and revise the health and safety file. This should continue for as long as
the principal designer’s appointment on the project lasts; or
(b) the principal contractor, where design work is carried out after the principal
designer’s appointment has finished and where changes need to be made to
the health and safety file. In these circumstances, it will be the principal
contractor’s duty to make those changes, but the designer must ensure that
the principal contractor has the appropriate information to update the file.
This information should be provided to the principal designer and principal
contractor as early as possible before the designer’s work ends on the project.
dutyholders
This Appendix gives guidance on the preparation, provision and retention of a health and safety file and the actions on each dutyholder.
Appendix 5 shows how the health and safety file relates to and influences other types of information during a construction project involving more than one contractor.
health and safety file
This Appendix gives guidance on the preparation, provision and retention of a health and safety file and the actions on each dutyholder.
Appendix 5 shows how the health and safety file relates to and influences other types of information during a construction project involving more than one contractor.
The principal designer must prepare the health and safety file. They are
accountable to the client and should liaise closely to agree the structure and
content of the file as soon as practicable after appointment. In preparing the file,
the principal designer should expect the client to provide any health and safety file
that may exist from an earlier project.
For the duration of the principal designer’s appointment, the principal
contractor plays a secondary role in ensuring the health and safety file is fit for
purpose. They must provide the principal designer with any relevant information that
needs to be included in the health and safety file.
The contractor has no specific duties placed on them in relation to the health
and safety file.
The file must contain information about the current project likely to be needed to ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion:
(a) a brief description of the work carried out;
The file must contain information about the current project likely to be needed to ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion:
(b) any hazards that have not been eliminated through the design and construction processes, and how they have been addressed (eg surveys or other information concerning asbestos or contaminated land);
The file must contain information about the current project likely to be needed to ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion:
(c) key structural principles (eg bracing, sources of substantial stored energy – including pre- or post-tensioned members) and safe working loads for floors and roofs;
The file must contain information about the current project likely to be needed to ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion:
(d) hazardous materials used (eg lead paints and special coatings);
The file must contain information about the current project likely to be needed to ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion:
(e) information regarding the removal or dismantling of installed plant and equipment (eg any special arrangements for lifting such equipment);
The file must contain information about the current project likely to be needed to ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion:
(f) health and safety information about equipment provided for cleaning or
maintaining the structure;
The file must contain information about the current project likely to be needed to ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion:
(g) the nature, location and markings of significant services, including underground cables; gas supply equipment; fire-fighting services etc;
The file must contain information about the current project likely to be needed to ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion:
(h) information and as-built drawings of the building, its plant and equipment (eg the means of safe access to and from service voids and fire doors).
The client must ensure that the principal designer prepares the health and safety
file for a project. As the project progresses, the client must ensure that the principal
designer regularly updates, reviews and revises the health and safety file to take
account of the work and any changes that have occurred. The client should be
aware that if the principal designer’s appointment finishes before the end of the
project, the principal designer must pass the health and safety file to the principal
contractor, who then must take on the responsibility for the file.
Information must be in a convenient form, clear, concise and easily understandable.
Where it is not possible to eliminate health and safety risks when preparing or
modifying designs, designers must ensure appropriate information is included in the
health and safety file about the reasonably practicable steps they have taken to
reduce or control those risks. This will involve liaising with:
(a) the principal designer, in helping them carry out their duty to prepare, update,
review and revise the health and safety file. This should continue for as long as
the principal designer’s appointment on the project lasts; or
(b) the principal contractor, where design work is carried out after the principal
designer’s appointment has finished and where changes need to be made to
the health and safety file. In these circumstances, it will be the principal
contractor’s duty to make those changes, but the designer must ensure that
the principal contractor has the appropriate information to update the file.
This information should be provided to the principal designer and principal
contractor as early as possible before the designer’s work ends on the project.
importer
The principal designer must also cooperate with the rest of the project team
and should expect their cooperation in return. Cooperation with the principal contractor is particularly important in agreeing the structure and content of the
information included in the file. Liaison with designers and other contractors is also
important. They may hold information that is useful for the health and safety file,
which may be difficult to obtain after they have left the project.
land survey
The file must contain information about the current project likely to be needed to ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion:
(a) a brief description of the work carried out;
(b) any hazards that have not been eliminated through the design and construction processes, and how they have been addressed (eg surveys or other information concerning asbestos or contaminated land);
(c) key structural principles (eg bracing, sources of substantial stored energy – including pre- or post-tensioned members) and safe working loads for floors and roofs;
(d) hazardous materials used (eg lead paints and special coatings);
(e) information regarding the removal or dismantling of installed plant and equipment (eg any special arrangements for lifting such equipment);
(f) health and safety information about equipment provided for cleaning or
maintaining the structure;
(g) the nature, location and markings of significant services, including underground cables; gas supply equipment; fire-fighting services etc;
(h) information and as-built drawings of the building, its plant and equipment (eg the means of safe access to and from service voids and fire doors).
The file must contain information about the current project likely to be needed to ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion:
(b) any hazards that have not been eliminated through the design and construction processes, and how they have been addressed (eg surveys or other information concerning asbestos or contaminated land);
level of detail
There should be enough detail to allow the likely risks to be identified and
addressed by those carrying out the work. However, the level of detail should be
proportionate to the risks. The file should not include things that will be of no help
when planning future construction work such as pre-construction information, the
construction phase plan, contractual documents, safety method statements etc.
Information must be in a convenient form, clear, concise and easily understandable.
method statement
There should be enough detail to allow the likely risks to be identified and
addressed by those carrying out the work. However, the level of detail should be
proportionate to the risks. The file should not include things that will be of no help
when planning future construction work such as pre-construction information, the
construction phase plan, contractual documents, safety method statements etc.
Information must be in a convenient form, clear, concise and easily understandable.
must
The client must ensure that the principal designer prepares the health and safety
file for a project. As the project progresses, the client must ensure that the principal
designer regularly updates, reviews and revises the health and safety file to take
account of the work and any changes that have occurred. The client should be
aware that if the principal designer’s appointment finishes before the end of the
project, the principal designer must pass the health and safety file to the principal
contractor, who then must take on the responsibility for the file.
Information must be in a convenient form, clear, concise and easily understandable.
non-core service disciplines
The file must contain information about the current project likely to be needed to ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion:
(g) the nature, location and markings of significant services, including underground cables; gas supply equipment; fire-fighting services etc;
pre-construction information
This Appendix gives guidance on the preparation, provision and retention of a health and safety file and the actions on each dutyholder.
Appendix 5 shows how the health and safety file relates to and influences other types of information during a construction project involving more than one contractor.
The principal designer must also cooperate with the rest of the project team
and should expect their cooperation in return. Cooperation with the principal contractor is particularly important in agreeing the structure and content of the
information included in the file. Liaison with designers and other contractors is also
important. They may hold information that is useful for the health and safety file,
which may be difficult to obtain after they have left the project.
The file must contain information about the current project likely to be needed to ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion:
(b) any hazards that have not been eliminated through the design and construction processes, and how they have been addressed (eg surveys or other information concerning asbestos or contaminated land);
The file must contain information about the current project likely to be needed to ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion:
(d) hazardous materials used (eg lead paints and special coatings);
The file must contain information about the current project likely to be needed to ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion:
(h) information and as-built drawings of the building, its plant and equipment (eg the means of safe access to and from service voids and fire doors).
There should be enough detail to allow the likely risks to be identified and
addressed by those carrying out the work. However, the level of detail should be
proportionate to the risks. The file should not include things that will be of no help
when planning future construction work such as pre-construction information, the
construction phase plan, contractual documents, safety method statements etc.
Information must be in a convenient form, clear, concise and easily understandable.
If a client disposes of their interest in the building, they must give the file to the
individual or organisation who takes on the client duties and ensure that the new
client is aware of the nature and purpose of the file. If they sell part of a building,
any relevant information in the file must be passed or copied to the new owner. If
the client leases out all or part of the building, arrangements should be made for
the file to be made available to leaseholders. If the leaseholder acts as a client for a
future construction project, the leaseholder and the original client must arrange for
the file to be made available to the new principal designer.
preparation and brief
The file must contain information about the current project likely to be needed to ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion:
(a) a brief description of the work carried out;
principal contractor
The principal designer must also cooperate with the rest of the project team
and should expect their cooperation in return. Cooperation with the principal contractor is particularly important in agreeing the structure and content of the
information included in the file. Liaison with designers and other contractors is also
important. They may hold information that is useful for the health and safety file,
which may be difficult to obtain after they have left the project.
The principal designer must also cooperate with the rest of the project team
and should expect their cooperation in return. Cooperation with the principal contractor is particularly important in agreeing the structure and content of the
information included in the file. Liaison with designers and other contractors is also
important. They may hold information that is useful for the health and safety file,
which may be difficult to obtain after they have left the project.
The principal designer must pass the updated file to the client at the end of the
project. In doing this, they should ensure the client understands the structure and
content of the file and its significance for any subsequent project. If the principal
designer’s appointment finishes before the end of the project, they must pass the
file to the principal contractor who must then take on responsibility for it. In doing
this, the principal designer should ensure the principal contractor is aware of any
outstanding issues that may need to be taken into account when reviewing,
updating and revising the file.
The principal designer must pass the updated file to the client at the end of the
project. In doing this, they should ensure the client understands the structure and
content of the file and its significance for any subsequent project. If the principal
designer’s appointment finishes before the end of the project, they must pass the
file to the principal contractor who must then take on responsibility for it. In doing
this, the principal designer should ensure the principal contractor is aware of any
outstanding issues that may need to be taken into account when reviewing,
updating and revising the file.
For the duration of the principal designer’s appointment, the principal
contractor plays a secondary role in ensuring the health and safety file is fit for
purpose. They must provide the principal designer with any relevant information that
needs to be included in the health and safety file.
For the duration of the principal designer’s appointment, the principal
contractor plays a secondary role in ensuring the health and safety file is fit for
purpose. They must provide the principal designer with any relevant information that
needs to be included in the health and safety file.
Where the principal designer’s appointment finishes before the end of the
project, the principal contractor must take on responsibility for ensuring that the file
is reviewed, updated and revised for the remainder of the project. At the end of the
project the principal contractor must pass the file to the client. In doing this, they
should ensure the client understands the structure and content of the file and its
significance for any subsequent project.
Where the principal designer’s appointment finishes before the end of the
project, the principal contractor must take on responsibility for ensuring that the file
is reviewed, updated and revised for the remainder of the project. At the end of the
project the principal contractor must pass the file to the client. In doing this, they
should ensure the client understands the structure and content of the file and its
significance for any subsequent project.
The client must ensure that the principal designer prepares the health and safety
file for a project. As the project progresses, the client must ensure that the principal
designer regularly updates, reviews and revises the health and safety file to take
account of the work and any changes that have occurred. The client should be
aware that if the principal designer’s appointment finishes before the end of the
project, the principal designer must pass the health and safety file to the principal
contractor, who then must take on the responsibility for the file.
Information must be in a convenient form, clear, concise and easily understandable.
The client must ensure that the principal designer prepares the health and safety
file for a project. As the project progresses, the client must ensure that the principal
designer regularly updates, reviews and revises the health and safety file to take
account of the work and any changes that have occurred. The client should be
aware that if the principal designer’s appointment finishes before the end of the
project, the principal designer must pass the health and safety file to the principal
contractor, who then must take on the responsibility for the file.
Information must be in a convenient form, clear, concise and easily understandable.
Once the project is finished, the client should expect the principal designer to
pass them the health and safety file. In cases where the principal designer has left
the project before it finishes, it will be for the principal contractor to pass the file to
the client.
Once the project is finished, the client should expect the principal designer to
pass them the health and safety file. In cases where the principal designer has left
the project before it finishes, it will be for the principal contractor to pass the file to
the client.
Where it is not possible to eliminate health and safety risks when preparing or
modifying designs, designers must ensure appropriate information is included in the
health and safety file about the reasonably practicable steps they have taken to
reduce or control those risks. This will involve liaising with:
(a) the principal designer, in helping them carry out their duty to prepare, update,
review and revise the health and safety file. This should continue for as long as
the principal designer’s appointment on the project lasts; or
(b) the principal contractor, where design work is carried out after the principal
designer’s appointment has finished and where changes need to be made to
the health and safety file. In these circumstances, it will be the principal
contractor’s duty to make those changes, but the designer must ensure that
the principal contractor has the appropriate information to update the file.
This information should be provided to the principal designer and principal
contractor as early as possible before the designer’s work ends on the project.
Where it is not possible to eliminate health and safety risks when preparing or
modifying designs, designers must ensure appropriate information is included in the
health and safety file about the reasonably practicable steps they have taken to
reduce or control those risks. This will involve liaising with:
(a) the principal designer, in helping them carry out their duty to prepare, update,
review and revise the health and safety file. This should continue for as long as
the principal designer’s appointment on the project lasts; or
(b) the principal contractor, where design work is carried out after the principal
designer’s appointment has finished and where changes need to be made to
the health and safety file. In these circumstances, it will be the principal
contractor’s duty to make those changes, but the designer must ensure that
the principal contractor has the appropriate information to update the file.
This information should be provided to the principal designer and principal
contractor as early as possible before the designer’s work ends on the project.
principal designer
The principal designer must prepare the health and safety file. They are
accountable to the client and should liaise closely to agree the structure and
content of the file as soon as practicable after appointment. In preparing the file,
the principal designer should expect the client to provide any health and safety file
that may exist from an earlier project.
The principal designer must prepare the health and safety file. They are
accountable to the client and should liaise closely to agree the structure and
content of the file as soon as practicable after appointment. In preparing the file,
the principal designer should expect the client to provide any health and safety file
that may exist from an earlier project.
The principal designer must also cooperate with the rest of the project team
and should expect their cooperation in return. Cooperation with the principal contractor is particularly important in agreeing the structure and content of the
information included in the file. Liaison with designers and other contractors is also
important. They may hold information that is useful for the health and safety file,
which may be difficult to obtain after they have left the project.
The principal designer must also cooperate with the rest of the project team
and should expect their cooperation in return. Cooperation with the principal contractor is particularly important in agreeing the structure and content of the
information included in the file. Liaison with designers and other contractors is also
important. They may hold information that is useful for the health and safety file,
which may be difficult to obtain after they have left the project.
The principal designer, in cooperation with other members of the project team,
must also ensure that the file is appropriately updated, reviewed and revised to
ensure it takes account of any changes that occur as the project progresses.
The principal designer, in cooperation with other members of the project team,
must also ensure that the file is appropriately updated, reviewed and revised to
ensure it takes account of any changes that occur as the project progresses.
The principal designer must pass the updated file to the client at the end of the
project. In doing this, they should ensure the client understands the structure and
content of the file and its significance for any subsequent project. If the principal
designer’s appointment finishes before the end of the project, they must pass the
file to the principal contractor who must then take on responsibility for it. In doing
this, the principal designer should ensure the principal contractor is aware of any
outstanding issues that may need to be taken into account when reviewing,
updating and revising the file.
The principal designer must pass the updated file to the client at the end of the
project. In doing this, they should ensure the client understands the structure and
content of the file and its significance for any subsequent project. If the principal
designer’s appointment finishes before the end of the project, they must pass the
file to the principal contractor who must then take on responsibility for it. In doing
this, the principal designer should ensure the principal contractor is aware of any
outstanding issues that may need to be taken into account when reviewing,
updating and revising the file.
For the duration of the principal designer’s appointment, the principal
contractor plays a secondary role in ensuring the health and safety file is fit for
purpose. They must provide the principal designer with any relevant information that
needs to be included in the health and safety file.
For the duration of the principal designer’s appointment, the principal
contractor plays a secondary role in ensuring the health and safety file is fit for
purpose. They must provide the principal designer with any relevant information that
needs to be included in the health and safety file.
Where the principal designer’s appointment finishes before the end of the
project, the principal contractor must take on responsibility for ensuring that the file
is reviewed, updated and revised for the remainder of the project. At the end of the
project the principal contractor must pass the file to the client. In doing this, they
should ensure the client understands the structure and content of the file and its
significance for any subsequent project.
Where the principal designer’s appointment finishes before the end of the
project, the principal contractor must take on responsibility for ensuring that the file
is reviewed, updated and revised for the remainder of the project. At the end of the
project the principal contractor must pass the file to the client. In doing this, they
should ensure the client understands the structure and content of the file and its
significance for any subsequent project.
The client must ensure that the principal designer prepares the health and safety
file for a project. As the project progresses, the client must ensure that the principal
designer regularly updates, reviews and revises the health and safety file to take
account of the work and any changes that have occurred. The client should be
aware that if the principal designer’s appointment finishes before the end of the
project, the principal designer must pass the health and safety file to the principal
contractor, who then must take on the responsibility for the file.
Information must be in a convenient form, clear, concise and easily understandable.
The client must ensure that the principal designer prepares the health and safety
file for a project. As the project progresses, the client must ensure that the principal
designer regularly updates, reviews and revises the health and safety file to take
account of the work and any changes that have occurred. The client should be
aware that if the principal designer’s appointment finishes before the end of the
project, the principal designer must pass the health and safety file to the principal
contractor, who then must take on the responsibility for the file.
Information must be in a convenient form, clear, concise and easily understandable.
Once the project is finished, the client should expect the principal designer to
pass them the health and safety file. In cases where the principal designer has left
the project before it finishes, it will be for the principal contractor to pass the file to
the client.
Once the project is finished, the client should expect the principal designer to
pass them the health and safety file. In cases where the principal designer has left
the project before it finishes, it will be for the principal contractor to pass the file to
the client.
If a client disposes of their interest in the building, they must give the file to the
individual or organisation who takes on the client duties and ensure that the new
client is aware of the nature and purpose of the file. If they sell part of a building,
any relevant information in the file must be passed or copied to the new owner. If
the client leases out all or part of the building, arrangements should be made for
the file to be made available to leaseholders. If the leaseholder acts as a client for a
future construction project, the leaseholder and the original client must arrange for
the file to be made available to the new principal designer.
If a client disposes of their interest in the building, they must give the file to the
individual or organisation who takes on the client duties and ensure that the new
client is aware of the nature and purpose of the file. If they sell part of a building,
any relevant information in the file must be passed or copied to the new owner. If
the client leases out all or part of the building, arrangements should be made for
the file to be made available to leaseholders. If the leaseholder acts as a client for a
future construction project, the leaseholder and the original client must arrange for
the file to be made available to the new principal designer.
Where it is not possible to eliminate health and safety risks when preparing or
modifying designs, designers must ensure appropriate information is included in the
health and safety file about the reasonably practicable steps they have taken to
reduce or control those risks. This will involve liaising with:
(a) the principal designer, in helping them carry out their duty to prepare, update,
review and revise the health and safety file. This should continue for as long as
the principal designer’s appointment on the project lasts; or
(b) the principal contractor, where design work is carried out after the principal
designer’s appointment has finished and where changes need to be made to
the health and safety file. In these circumstances, it will be the principal
contractor’s duty to make those changes, but the designer must ensure that
the principal contractor has the appropriate information to update the file.
This information should be provided to the principal designer and principal
contractor as early as possible before the designer’s work ends on the project.
Where it is not possible to eliminate health and safety risks when preparing or
modifying designs, designers must ensure appropriate information is included in the
health and safety file about the reasonably practicable steps they have taken to
reduce or control those risks. This will involve liaising with:
(a) the principal designer, in helping them carry out their duty to prepare, update,
review and revise the health and safety file. This should continue for as long as
the principal designer’s appointment on the project lasts; or
(b) the principal contractor, where design work is carried out after the principal
designer’s appointment has finished and where changes need to be made to
the health and safety file. In these circumstances, it will be the principal
contractor’s duty to make those changes, but the designer must ensure that
the principal contractor has the appropriate information to update the file.
This information should be provided to the principal designer and principal
contractor as early as possible before the designer’s work ends on the project.
principal works
Where it is not possible to eliminate health and safety risks when preparing or
modifying designs, designers must ensure appropriate information is included in the
health and safety file about the reasonably practicable steps they have taken to
reduce or control those risks. This will involve liaising with:
(a) the principal designer, in helping them carry out their duty to prepare, update,
review and revise the health and safety file. This should continue for as long as
the principal designer’s appointment on the project lasts; or
(b) the principal contractor, where design work is carried out after the principal
designer’s appointment has finished and where changes need to be made to
the health and safety file. In these circumstances, it will be the principal
contractor’s duty to make those changes, but the designer must ensure that
the principal contractor has the appropriate information to update the file.
This information should be provided to the principal designer and principal
contractor as early as possible before the designer’s work ends on the project.
project
The principal designer must also cooperate with the rest of the project team
and should expect their cooperation in return. Cooperation with the principal contractor is particularly important in agreeing the structure and content of the
information included in the file. Liaison with designers and other contractors is also
important. They may hold information that is useful for the health and safety file,
which may be difficult to obtain after they have left the project.
The principal designer, in cooperation with other members of the project team,
must also ensure that the file is appropriately updated, reviewed and revised to
ensure it takes account of any changes that occur as the project progresses.
The principal designer must pass the updated file to the client at the end of the
project. In doing this, they should ensure the client understands the structure and
content of the file and its significance for any subsequent project. If the principal
designer’s appointment finishes before the end of the project, they must pass the
file to the principal contractor who must then take on responsibility for it. In doing
this, the principal designer should ensure the principal contractor is aware of any
outstanding issues that may need to be taken into account when reviewing,
updating and revising the file.
Where the principal designer’s appointment finishes before the end of the
project, the principal contractor must take on responsibility for ensuring that the file
is reviewed, updated and revised for the remainder of the project. At the end of the
project the principal contractor must pass the file to the client. In doing this, they
should ensure the client understands the structure and content of the file and its
significance for any subsequent project.
The health and safety file is defined as a file appropriate to the characteristics of
the project, containing relevant health and safety information to be taken into
account during any subsequent project. The file is only required for projects
involving more than one contractor.
The client must ensure that the principal designer prepares the health and safety
file for a project. As the project progresses, the client must ensure that the principal
designer regularly updates, reviews and revises the health and safety file to take
account of the work and any changes that have occurred. The client should be
aware that if the principal designer’s appointment finishes before the end of the
project, the principal designer must pass the health and safety file to the principal
contractor, who then must take on the responsibility for the file.
Information must be in a convenient form, clear, concise and easily understandable.
Once the project is finished, the client should expect the principal designer to
pass them the health and safety file. In cases where the principal designer has left
the project before it finishes, it will be for the principal contractor to pass the file to
the client.
project information
The file must contain information about the current project likely to be needed to ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion:
(e) information regarding the removal or dismantling of installed plant and equipment (eg any special arrangements for lifting such equipment);
project team
The principal designer must also cooperate with the rest of the project team
and should expect their cooperation in return. Cooperation with the principal contractor is particularly important in agreeing the structure and content of the
information included in the file. Liaison with designers and other contractors is also
important. They may hold information that is useful for the health and safety file,
which may be difficult to obtain after they have left the project.
The principal designer, in cooperation with other members of the project team,
must also ensure that the file is appropriately updated, reviewed and revised to
ensure it takes account of any changes that occur as the project progresses.
project team member
The principal designer, in cooperation with other members of the project team,
must also ensure that the file is appropriately updated, reviewed and revised to
ensure it takes account of any changes that occur as the project progresses.
reasonably practicable
Where it is not possible to eliminate health and safety risks when preparing or
modifying designs, designers must ensure appropriate information is included in the
health and safety file about the reasonably practicable steps they have taken to
reduce or control those risks. This will involve liaising with:
(a) the principal designer, in helping them carry out their duty to prepare, update,
review and revise the health and safety file. This should continue for as long as
the principal designer’s appointment on the project lasts; or
(b) the principal contractor, where design work is carried out after the principal
designer’s appointment has finished and where changes need to be made to
the health and safety file. In these circumstances, it will be the principal
contractor’s duty to make those changes, but the designer must ensure that
the principal contractor has the appropriate information to update the file.
This information should be provided to the principal designer and principal
contractor as early as possible before the designer’s work ends on the project.
related
The contractor has no specific duties placed on them in relation to the health
and safety file.
roof structure
The file must contain information about the current project likely to be needed to ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion:
(a) a brief description of the work carried out;
(b) any hazards that have not been eliminated through the design and construction processes, and how they have been addressed (eg surveys or other information concerning asbestos or contaminated land);
(c) key structural principles (eg bracing, sources of substantial stored energy – including pre- or post-tensioned members) and safe working loads for floors and roofs;
(d) hazardous materials used (eg lead paints and special coatings);
(e) information regarding the removal or dismantling of installed plant and equipment (eg any special arrangements for lifting such equipment);
(f) health and safety information about equipment provided for cleaning or
maintaining the structure;
(g) the nature, location and markings of significant services, including underground cables; gas supply equipment; fire-fighting services etc;
(h) information and as-built drawings of the building, its plant and equipment (eg the means of safe access to and from service voids and fire doors).
The file must contain information about the current project likely to be needed to ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion:
(c) key structural principles (eg bracing, sources of substantial stored energy – including pre- or post-tensioned members) and safe working loads for floors and roofs;
should
The principal designer must prepare the health and safety file. They are
accountable to the client and should liaise closely to agree the structure and
content of the file as soon as practicable after appointment. In preparing the file,
the principal designer should expect the client to provide any health and safety file
that may exist from an earlier project.
The principal designer must pass the updated file to the client at the end of the
project. In doing this, they should ensure the client understands the structure and
content of the file and its significance for any subsequent project. If the principal
designer’s appointment finishes before the end of the project, they must pass the
file to the principal contractor who must then take on responsibility for it. In doing
this, the principal designer should ensure the principal contractor is aware of any
outstanding issues that may need to be taken into account when reviewing,
updating and revising the file.
There should be enough detail to allow the likely risks to be identified and
addressed by those carrying out the work. However, the level of detail should be
proportionate to the risks. The file should not include things that will be of no help
when planning future construction work such as pre-construction information, the
construction phase plan, contractual documents, safety method statements etc.
Information must be in a convenient form, clear, concise and easily understandable.
Where it is not possible to eliminate health and safety risks when preparing or
modifying designs, designers must ensure appropriate information is included in the
health and safety file about the reasonably practicable steps they have taken to
reduce or control those risks. This will involve liaising with:
(a) the principal designer, in helping them carry out their duty to prepare, update,
review and revise the health and safety file. This should continue for as long as
the principal designer’s appointment on the project lasts; or
(b) the principal contractor, where design work is carried out after the principal
designer’s appointment has finished and where changes need to be made to
the health and safety file. In these circumstances, it will be the principal
contractor’s duty to make those changes, but the designer must ensure that
the principal contractor has the appropriate information to update the file.
This information should be provided to the principal designer and principal
contractor as early as possible before the designer’s work ends on the project.
special structures
The file must contain information about the current project likely to be needed to ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion:
(a) a brief description of the work carried out;
(b) any hazards that have not been eliminated through the design and construction processes, and how they have been addressed (eg surveys or other information concerning asbestos or contaminated land);
(c) key structural principles (eg bracing, sources of substantial stored energy – including pre- or post-tensioned members) and safe working loads for floors and roofs;
(d) hazardous materials used (eg lead paints and special coatings);
(e) information regarding the removal or dismantling of installed plant and equipment (eg any special arrangements for lifting such equipment);
(f) health and safety information about equipment provided for cleaning or
maintaining the structure;
(g) the nature, location and markings of significant services, including underground cables; gas supply equipment; fire-fighting services etc;
(h) information and as-built drawings of the building, its plant and equipment (eg the means of safe access to and from service voids and fire doors).